::: Progress Photos of the TSFSP Project - February 2008 :::

 

Project:
     THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work of the TSFSP Project

Progress work at TSFSP Project taken at St. Francis Road.

Progress work at TSFSP Tower 2 Taken at St. Francis Road.

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work at TSFSP Tower 1

Progress work on installation of windows at Tower 1 taken at corner of St. Francis St. & Internal Road.

Progress work on installation of windows at Tower 1 taken at Shangri-la Plaza

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work at TSFSP Project

On-going installation of forms at 8th Floor Swimming Pool Area taken at 10 Floor Tower 2

Installed of MEPF conduits at slab and beams ready for concrete pouring at 52nd Floor Tower 2

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work at TSFSP Project

Installed electrical roughing-ins ready for concrete pouring at 42nd Floor Tower 1

On-going leveling of newly poured concrete on slab and beams at 42nd Floor T1

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Installation of Viscous Damper

On-going hauling of Viscous Damper at 34th Floor Tower 1

Installed of MEPF conduits at slab and beams ready for concrete pouring at 52nd Floor Tower 2

 

Project:
     THE ST. FRANCIS SHANGRI-LA PLACE

Installation of Viscous Damper

On-going installation of Viscous Damper with FIP’s Representative

On-going installation of Viscous Damper

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Installation of Viscous Damper

Installed Viscous Damper at 34th-35th Floor Tower 2

Installed Viscous Damper at 34th-35th Floor Tower 2

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work at TSFSP-Hotel Link Bridge Project

Progress work at TSFSP-Hotel Link Bridge taken at Shangri-la Plaza

Progress work at TSFSP-Hotel Link Bridge taken at Shangri-la Plaza

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work at TSFSP-Hotel Link Bridge Project

On-going finishing works, ready for installation of lighting fixtures at Link Bridge

On-going finishing works at the Link Bridge

 

Project:
THE ST. FRANCIS SHANGRI-LA PLACE

Progress Work at TSFSP-Hotel Link Bridge Project

Installed glass balustrade and stainless handrails at Link Bridge

Installed escalators at Link Bridge